| Item |
Action Taken |
Date |
Status |
| BMS Spacer Design for cut-out in Sector 8 |
|
|
pending |
| Position of connections and electronics in BML, BMS, BOL |
|
June Muon Week |
pending decision (and cost) on mezzanine-CSM cable |
| Evaluate consequences on number of chambers w/o diagonal in-plane beams, due to layout changes |
|
|
pending |
| New design for EIL4 supports in feet sectors and sectors 1,7,9 |
EIL4 note and maquettes have been updated |
|
pending |
| Clearance problems in BMF installation |
TC agrees to reduce thickness of cable tray; RPC to follow up |
|
pending |
| Conflict between EES and connection box bolts |
Change in connection box design, needs to be re-evaluated |
December |
pending |
| Conflict between feet and low rapidity forward alignment ray |
ECR has been issued |
next week |
pending |
| Increased size of connection boxes and voussoirs interferes with BIR chambers |
Asked Magnet PL to make an ECR |
December |
pending |
| Access scenarios to all barrel chambers |
preliminary access way to be prepared |
December |
pending |
| Need access to front-end electronics in EIL1-EIS1 (high rad area) |
access scenario to be prepared |
December |
pending |
| Check deformations of EIL4 and EES, EEL frames, to ensure design of chambers and mounting can start |
|
end October |
prepared by Spigo |