Goal: Optical
instrumentation of 65 barrel modules
Schedule of operations:Starting in August 1999 and ending in July 2002 (3 years)
- There will be 8 periods of 18 weeks (16 of operations + 2 of setup) (msproj file, pdf)
- In each period of 18 weeks.
- 8 barrel modules will be instrumented and calibrated (msproject file, pdf)
- Assembly sequence over 2 barrel modules (msproject file, pdf)
- Description of the various assembly tasks in table format (html)
Storage:In Buildgs 180 , 175 and 185 in CERN Meyrin
Available material:material (tiles, fibres, modules,tables,....) , pdf file
Quality Control: There are various QC steps during instrumentation of the barrel modules.
Production monitor:
A task
data sheet for each module has to be filled during instrumentationnd
an overall Production
monitor page are used.
Photos during production:here
Cern Tiles Group (excel