Page maintained by: I.Efthymiopoulos (last update: May 19, 1997)
Machine development days: 2 July (8:00-16:00), 9 July (8:00-16:00), 23 July (8:00 - 16:00)
We have allocated this test beam period, but we might not use it if all go well with the SPS schedule
Special beam requests:
The exact times for the special beams will be discussed again following the genaral SPS schedule.
Note: For the ANL module the tubes and connections for the Cs Calibration have to be installed before the module is put on the table.
There have been several proposals/possibilities for the installation of the two extended barrel modules on the scanning table. Here is the list followed by some comments.
|
|
| 3d view of the module setup on the table.(beam
left is on the left of the figure)
The ITC plug is on the left side of the modules but not shown here. |
It has the dissadvantage that the top extended barrel module will suffer from the energy leakage on the top.
The problem now is that the weight is totally off-center and we are close to the limit for the operation of the jacks. I've spoken with the CERN engineers and they wouln'd be in favour of such a solution.
![]() |
![]() |
|
3d view (beam left is to the left of the picture) |
2d view |
The exact dimensions of the module installation can be found in ( figure ).
With this solution the problem with the weight being off-center is solved (not completely, but now we can compensate the small difference by puting an extra weight on the empty side of the table - far left). The CERN engineers believe that we can pass the security inspection. The only problem is to guarantee the stability of the two ext. barrel modules (not sliding in front) but a possible solution was proposed which they will work out in detail.
There are though few problems with this setup which need answers from the various sub-system experts:
It is certainly true that these two problems and in particular the second one, (and perhaps others that we might have not seen so far), are rather important during the installation phase. But is also true that this configuration is rather advantageous from the quality of the physics data we can take and from the fact that we can compare in almost the same way the two modules and extract valuable results.
Regardless the modules configuration, there is a proposal to ecquip 15 channels of the middle module with the new bi-gain/12bit ADC readout. The actual electronics are in production these days, the first test bench results look rather promising and the people who are working on this are confident that they can meet the dates to have them installed from the beginning of the period.
The proposal was to ecquip 3 full consecutive towers:
![]() |